Concrete Floor Construction Plan

Section 1. Programming narrative

  1.  Purpose

The purpose of preparing this program is to guide the construction and meet the quality requirements.

  1. the preparation of the basis

Basis of preparation: concrete structure construction specifications, construction design requirements, P&G company requirements.

  1. Construction focus and difficulties

(1). Ground elevation control

(2). Land flatness control

(3). Night construction and rainproof measures

(4). Finished product protection

Section 2. Concrete floor construction methods

(1). To prevent concrete flooring hollow drums, the mat surface should be cleaned to remove slicks and oil stains; the substrate should be moistened with water.

(2). The ground concrete grade is C30. 3.

(3). The slump of freshly poured concrete should be controlled between 10-300px when using commercial concrete.

(4). The mud content of freshly poured concrete aggregate should be controlled within 1%, and the maximum aggregate size should be controlled within 75px. (5) Freshly poured concrete should be used as a concrete slab.

(5). freshly poured concrete should be pounded by plate vibrator or steel roller, in the part that can’t be compacted by roller, it can be firstly patted by wooden crab, and then leveled by long yardstick, the surface level of freshly poured concrete should be controlled promptly after pounding, and the deviation should be adjusted, the flatness of freshly poured concrete surface should be controlled within 3mm/3m.

(6). concrete surface excess secretion should be removed in a timely manner, during construction can be used to absorb excess secretion pipe, can also be used to absorb sponge, transfer excess secretion.

Concrete Floor Construction Plan

Flooring construction technical requirements

slurry removal

The floating slurry on the surface of freshly poured concrete should be cleaned up without affecting the quality of the ground. After the initial setting period of the freshly poured concrete, trowel off the floating pulp layer evenly with a disc mounted on the concrete surface.

Pulp lifting and surface polishing

Use trowel to press and grind the pulp according to the spreading process, and then press and grind the pulp vertically and horizontally at least twice.

After the ground trowel construction, depending on the hardening of the concrete, the surface of the trowel can be used to finish the surface. Adjust the blade angle and speed of the trowel depending on the hardening of the concrete. Adjust the blade angle once at the beginning of each finish to avoid damage to the flooring. It is the final touch up of the flooring, so it is important to select a responsible person to do the work.

Mechanical work to deal with the part is not by artificial iron trowel for calendering treatment, the construction of artificial light should be slightly earlier than the mechanical, the operation does not allow the appearance of blister and light traces, and keep the joints smooth. In order to ensure the construction quality of the whole ground.

Maintenance of flooring

The post-care is directly related to, especially when the construction is done in warmer weather, the maintenance of the flooring should be strengthened. In order to ensure the stable growth of the strength of the concrete flooring, flooring construction completed 5-6 hours, you can carry out maintenance, flooring maintenance can be used in the method of coating the surface of the maintenance agent, can also be directly covered with water or film method of maintenance, flooring maintenance time should generally be not less than 7 days.

During the maintenance period, the flooring surface should prevent the pollution of oil, mortar, dyes, corrosive liquids, etc. during the construction of other types of work, and the equipment that must pass through the flooring surface should be equipped with protective facilities. During the maintenance period, the flooring surface is strictly prohibited to carry weight and cross operation.

Section 3: Concrete ground flatness control

  1. Flatness design requirements

The floor of the production workshop is required to be polished with vibrating, and the flatness is strictly guaranteed, and the height difference should not be more than 3mm with 3m ruler.

  1. Requirements for construction preparation

Must be operated by skilled concrete workers, before construction, must be clear about the contents of the handover, grasp the essentials.

Before construction, personnel, materials, machinery, temporary electricity, fence and other preparatory work must be done.

  1. Pouring order

Natural division into blocks according to the cast-in-band, with pouring between the blocks or pouring at intervals on the same side.

  1. Zero board elevation control settings and levelness control

Construction process

Bedding construction, bolt angle iron production → bolt, angle iron installation → elevation measurement → concrete pouring, leveling → angle iron dismantling, secondary leveling → maintenance → inspection and acceptance.

(1) Adopt specific elevation control bolts, with angle iron for elevation control, the distance between angle iron is 3m, use 6m leaning feet, leveling according to the preset elevation.

  1. 1.Determining the form of the height adjustment screw

Holding special meetings with construction team leaders and project managers to study bolt fabrication methods

Adjustment bolts are reliable, practical and easy to operate

  1. Determine the distance between the angle iron and its support points

Determine the spacing of angle irons and their support points by consulting information

No deformation of the angle iron during construction, effective control of the elevation

  1. Development of fixing method for the mediation bolts

Drill a hole in the bedding, one size smaller than the bolt diameter, and nail the bolt into the hole.

Stable bolts do not wobble, ensure accurate elevation

  1. Leveling of angle iron using a spirit level

Leveling of angle iron using a spirit level

Ensure that the concrete elevation of the floor is accurate

  1. Concrete levelling with 6m yardstick

6m levelling using 6m levelling feet on a track made of angles.

Ensure that the concrete finish of the floor meets the requirements

  1. Removal of angle iron

After the concrete leveling is completed, remove the angle iron and level the concrete twice.

Implementation I. The flatness of the concrete surface meets the requirements, the angle iron turnover use

That is, two silk caps are set on the head of the Φ14 bolt, and the angle iron is sandwiched between the two caps, the lower cap is adjusted in height, and the upper cap is used to fix the angle iron. The following picture.

Implementation II. Determining the spacing of angle irons and their support points

After fully considering the rigidity properties of L30 angle iron and the amount of material, we decided to set the support points on the 6m long angle iron with a spacing of 1900mm.

Implementation III. Development of fixing methods for mediation bolts

After discussion among the QC team members, it was decided that the sample would be placed on the pad first, then the Φ12 drill bit would be used to drill holes according to the release position, and then the Φ14 adjusting bolt would be nailed into the concrete pad. During the construction, if there is any loosening, the bolt will be nailed into the gap between the bolt and the hole for reinforcement.

Implementation IV. Adopt level to level the angle iron.

During the construction, the technician uses C32II level to level the angle iron, meanwhile, the builder adjusts the adjusting nut according to the technician’s instruction, adjusts the height of the angle iron, and then tightens the fixing nut after checking. During the leveling process, each adjustment point is carefully calibrated to the elevation. As shown at right.

Implementation V. Using 6m leaning feet for concrete leveling

The concrete is poured after the check of the elevation is completed. After the concrete is paved, three workers simultaneously level the concrete surface using a 6m yardstick along a “track” formed by an angle iron. The concrete protruding from the ground elevation is scraped off, while another person is responsible for filling the depressed part, and then the three levelling workers scrape the concrete twice.

Implementation VI. Removal of angle iron

(1). After the concrete is poured and levelled, the angle iron is removed when the concrete begins to set. Use a ruler to level the concrete surface of the angle iron again along the formed concrete surface. At the same time, clean the angle iron for turnover.

(2). Use aluminum alloy square pass to level the concrete along the surface of the angle iron, and drive at least 2 to 3 times. The first time with 3-5m long aluminum alloy square leveling, in the process of leveling for poor material for the place to be driven with the Tim, in the concrete close to the initial set and above the basic can take off the angle steel, beyond the concrete surface of the support steel bent into the concrete with the steel to move the child bent. In the process of fine levelling, where the small error cannot be added to the concrete, level it with 1:1 cement dry sand dust, and after leveling, grind the whole with pulp extractor to extract pulp again, and then level it with aluminum alloy square when the extracting is finished. When the concrete is first set, then use the polishing machine to collect light in a large area, because the machine can’t put in place the corners, adopt manual calendering treatment in advance.

(3). During the second time of leveling, the surveyor must set up the leveling error in the whole process, in order to ensure the leveling, every 1m or so must measure a point, and deal with the part that exceeds the standard in time during the measuring process.

Concrete Floor Construction Plan

  1. Protection of finished concrete slab

(1). Adopt the partition responsible for the management, who is responsible for the operation, and set up supervisors to follow up and inspect the protection of the finished products in the operation area every day, and order rectification in time when violation is found.

(2). for there are heavy objects, easy to cause heavy objects hit the ground operations, the construction must be on the ground before the laying of wooden plates before construction.

(3). for easy to cause ground contamination but there is no heavy work, must be laid before the construction of the colored cloth to protect the ground from pollution.

(4). for the pollution and the existence of heavy work, must be laid before the construction of colored strips of cloth and then lay the wooden plate before construction.

  1. Concrete maintenance

(1). 24 hours after concrete pouring is completed, watering is used to cover the plastic film for water conservation maintenance.

(2). In order to ensure the quality of flooring maintenance, adopt special sprinkling maintenance. Watering should be done frequently and sparingly, and the water for maintenance should be the same as that for mixing.

(3). The curing period is not less than 21 days, and measures are taken to protect the poured concrete from the damage of the upper construction.

(4). The concrete shall not be stepped on or installed with formwork and support before its strength reaches 1.2N/mm2.

Concrete Floor Construction Plan

Section 4: Concrete ground at night and rainproof construction measures

Night construction measures

  1. Concrete pouring time is scheduled at noon, leveling and light harvesting will be done at night.
  2. Before the night construction, sufficient lighting should be prepared.
  3. If you are notified of power failure, no concrete construction will be arranged.
  4. Keep the construction channel clear.
  5. Schedule managers for duty
  6. Arrange electricians, reinforcement workers, carpenters on duty.
  7. Prepare construction materials and equipment in advance.

Rainproof measures

  1. As flooring concrete is an open-air operation, it is necessary to ensure that the construction of flooring concrete will not be affected by the rain, keep track of the weather and avoid construction on rainy days.
  2. In case of temporary showers, take the following rainproof measures before construction to prepare rainproof materials.

Prepare 700 square meters of rain tarpaulin, set up a temporary rain shelter to protect the poured ground.

Section 5. Concrete ground finished product protection

  1. the completed ground should be timely erected finished protective fence, in the personnel frequent access to the door hanging eye-catching protection signs, prohibit personnel from entering the maintenance period of the flooring, and assign someone responsible for care.
  2. before lifting the steel structure, the flooring is covered with film, full of geotextile, densely paved with 18-thick wood templates to protect the flooring from impact, and the boards are nailed firmly with steam nails to form a piece, in the process of lifting, measures are taken to prevent components from falling to the ground, such as tools and screws (caps) packed with special tool bags, and assign someone to take care of it.
  3. When welding steel structure, take fire-fighting measures, including setting fire extinguisher, supervising the welding fire scene by safety personnel, and using color steel plate blocking measures below the fire.
  4. For electromechanical installation, when the electromechanical is tested by hydraulic pressure, arrange the water inlet and outlet position to avoid the test water flowing into the floor, and at the same time, place the receiving bucket at the joint position to prevent the water from leaking into the ground in case of pollution.